1. Call to Order and Roll Call of Members
2. Record of Members Present and Absent: Stout,
Reed, Bess, McElroy & Ostrander
3. Discussion and Approval of Bids for the 2018 Bond Issue Building
Projects
-- Approved, low bids for phase I construction
(voters approved in
Feb. 2018)
* KSL (Bartlesville) site work $477K
* Brewer Construction - concrete $363K
* Brewer Construction - metal buildings $769K (Alliance Steel in OKC
is supplier)
Additional Notes:
- Some site work has already begun
- Gravel construction road nearly complete (to CUE from 126th)
- City building permit price not set yet
- contingency budget $30K for this first phase
- more bids in August for additional work
- some design delays (KKT)
- will start at CUE next week, then HS add-on, then band/ag buildings
- Also expect bids in September for track rehab
4. Adjournment -- 12:15pm
By: __________________________
Lance West, Superintendent
Posted this ___ date of _____________ _____ at _____ x.m. on the door
of the Education
Service Center, 1902 W Maple, Collinsville, OK 74021.
Ted
Wright comments in purple
|