Collinsville,
Oklahoma September 23, 2009 City Street Overlay Plan |
Asphalt
Overlays Might Begin
Before End of The Year
(Depending on Tulsa County
Scheduling)
Funded
by Additional City Sales Tax
This web site is brought to you by the Newspaper Museum In Collinsville and the other advertisers appearing on these pages. If you would like to provide news content or advertisements ... call Ted Wright (918) 371-1901 or send email to wrightted@aol.com. 1110 W. Main, Collinsville, OK 74021 Frequently Asked Questions |
Home
(email questions/comments to wrightted@aol.com). Ted Wright -- last update 9/23/2009 (StreetOverlayPlan.html) www.cvilleok.com Copyright 2009 -- Collinsville, Oklahoma |
|
This page
sponsored in part by:
www.collinsvillefh.com
(With Recent Obituaries)
Newly
Remodeled Facilities at 13th & Main
Jim R. Dolton
Funeral Director/Owner
Melvin Lowe - Funeral Director
Christy Harris - Funeral Director
Mary Blythe - Office Manager-Collinsville
Funeral Home
Betty Littler - Office Manager-Oologah Funeral Home
We Accept All Pre-Arrangements
City
of Collinsville Overlay Project | ||
Street | Blocks | |
1 | Maple - 20th to 13th | 8 |
2 | Maple - 5th to 6th | 1 |
3 | Walnut - 5th to 9th | 4 |
4 | Oak - 6th to 7th | 1 |
5 | Center -10th to 11th | 1 |
6 | Spring - 14th to 15th | 1 |
7 | 6th St . - Oak to Maple | 2 |
8 | 7th St. - Broadway to Oak | 1 |
9 | 11th St. - Spring to Center | 1 |
10 | 11th St. - Pearl to Oak | 4 |
11 | 13th St. - Broadway to Oak | 1 |
12 | 14th St. - Walnut to Maple | 1 |
13 | 15th At. - Spring to Main | 2 |
14 | 15th St. - Exchange to Union | 2 |
15 | 19th St. - Union to Broadway | 6 |
16 | 22nd St. Brook to Prarie | 2 |
17 | 10th St. Center to South | 2 |
18 | Spring - 10th to 11th | 1.5 |
19 | 16th St. - Main to Spring | 2 |
(Prarie View Addition below) | ||
20 | "H" Ave. - Center to Brook | 2 |
21 | "G" Ave. - Spring to Brook | 2 |
22 | "F" Ave. - Spring to Brook | 3 |
23 | East Spring - "D" to "H" Ave. | 4 |
Total | 54.5 |
This
plan for adding a new asphalt overlay to city streets was provided by the City
of Collinsville this week. I have not seen the plan (generated by city street
supervisor Steve Jones) discussed before the city commission since July so will
assume it is tentative pending formal approval. The funding for the asphalt material
comes from the additional city sales tax approved by voters back in April 2009.
Several other city improvements are also still pending: jail, splash pad, skate
park, playgrounds, 19th St. Bridge replacement, sidewalk to park, 2 block extension
of Main Street streetscape, ...etc. -- Ted Wright 9/23/2009 |
Just wondering: are the city north - south numbered roads officially "streets" or "avenues"?
This map has a mix of both. I've always know them as St. but I guess maybe the Tulsa Co / 911 system makes them Ave? or would that even apply in town? (i.e it's either 19th St. or 113th E. Ave)-- Ted
cvilleok.com
viewer comments |
Ted: Just read your article and looked at the map outlined by the city as to the asphalt overlays which are upcoming. One street that I can't understand why it is not being considered being resurfaced is 17the from Broadway north to Maple. That street runs just west of my house, but that is not my concern. 17th is a major school bus route and delivery route for Wilson Elementary School. It isn't the worst street in town, but is fast crumbling and if it isn't fixed now it probably will be later. Our busses certainly deserve a better street. Thanks Ron Evans. (9/24/2009) |