Tentative Streetscape Schedule
Received Monday 4:10pm 5-5-2008
From Bryant & Bryant Construction

Collinsville Main Street Enhancement Project
Weekly Schedule

All Activities are Dependent on weather conditions being suitable for the tasks, and not affecting the technical specifications.
Due to Complications on the project we will be removing all of the concrete work that BBCI has done. Due to grade elevations, and the air content in the concrete.


May 5 Work on north side of main between 11th & 12th getting curb & gutter and sidewalk ready.


May 6 Pour curb & gutter and grade sidewalk in front of the stores.


May 7 Start in the parking area between 11th & 10th and pour sidewalk on east end and block between 11th & 12th.


May 8 Need to test dirt and pack rock in the parking area between 10th & 11th.

May 9 Start setting curb & gutter between 10th & 11th from the west going east.

Previous Coverage

This web site is brought to you by the Newspaper Museum In Collinsville and the other advertisers appearing on these pages. If you would like to provide news content or advertisements ... call Ted Wright (918) 371-1901 or
send email to wrightted@aol.com.
1110 W. Main, Collinsville, OK 74021
Home
(email questions/comments to wrightted@aol.com).
Ted Wright -- last update 5/5/2008 (Streetscape5-5Sched.html) www.cvilleok.com

Copyright 2008 -- Collinsville, Oklahoma
Google
Web www.cvilleok.com
Note: I have photos and other info in progress but wanted to get this schedule online as soon as I found it in my email inbox. -- Ted 5:20 Monday